One sheet, A4 layout. Scroll inside the page to read it.
SAMPLE
Work done
Extra double boarding to the plant room after late drawing revision SI-14.
DAYWORK SHEET
| Sheet no. | DW-11 | Date | Tue 3 Nov 2026 |
|---|---|---|---|
| Job | Parkside Health Centre, Doncaster | ||
| Contractor | Northvale Building Ltd | ||
| Subcontractor | Kieran Hatch, drylining and plastering | ||
| Where | Plant room, level 1 | Instruction | SI-14 |
| Variation | VAR-03 | ||
Extra double boarding to the plant room after late drawing revision SI-14.
| Labour | |
|---|---|
| Kieran Hatch | 8 hours |
| Danny Cole | 8 hours |
| Total | 16 hours |
| Plant | None |
|---|---|
| Materials | 12 sheets 15mm board 1 box of screws |
Acknowledged by (site manager)Name and date
This sheet records the labour, plant and materials shown. It does not agree that the work is a variation, the rates, or payment. SAMPLE sheet with fictional details.
Quantities only. Pricing is done later, at the contract's daywork rates.
Next: send for acknowledgement Back to the sheet